What's new in Production Process Planning 2.7
In Production Process Planning 2.7, you can:
Add a configurator context with Product Configurator variant information to a work package.
Select operations in a product BOP, process station, or process resource and drag-and-drop them to:
Allocate selected operations from the product BOP to a process station or process resource.
Move selected operations between process stations or process resources.
Quickly set capacity for part-time operators, and determine how many operators are needed in a plan.
Create a process resource, and indicate whether it is a machine or human process resource.
Search for operations in a product BOP.
Known issues and workarounds
In Easy Plan 2.11, changing time units and opening a Manufacturing Change Notice (MCN) from the Production Process Planning header area are not supported using the Internet Explorer browser. Use a different browser to perform these tasks.